Check out the road work that could affect your travel

Daylight/Overnight Hours
Route 68 between Interstate 44 and Route 8 – Pedestrian improvements and resurfacing continues.
    *Resurfacing will take place the week of October 2. One lane will be open, with crews and a pilot car guiding traffic through the work area.  The project is scheduled for completion in the fall.

Daylight Hours
Route 63 between the Rolla city limits and Route CC in Texas County – Roadway resurfacing continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.

Route E between Route Y and County Road 538 in Maries County – Roadway maintenance will take place Monday, October 2 through Thursday, October 5. One lane will be open, and crews will flag traffic through the work area.

Route J between Route K and Route M – Roadside maintenance will take place Monday, October 2 through Thursday, October 12. One lane will be open, and crews will flag traffic through the work area.